"Nizhnekamskneftekhim" INC completing erection of second polystyrene production facility


It keeps to the schedule.
The Facility’s construction budget amounts to RUR 1566m. To-date, it consumed over 70% of the planned investment. Polymerization section equipment has been fully installed; granulation and packaging section equipment is being installed and piped; cooling tower and bead product silos are under erection.
PS granulation and packaging line at second facility is being equipped with a dust collecting system. Product packaging and palletizing will be automatic.
According to A. Minullin, PS PLANT director, erection of metal structures, instrumentation and electrical equipment is planned for completion in current March-April. Precommissioning is scheduled for beginning in May.
With second facility in operation, PS capacity will total 100 000 TPA.

Press service
Nizhnekamskneftekhim Inc.
423574, R.F. Republic of Tatarstan, Nizhnekamsk, Nizhnekamskneftekhim Inc.
Tel.: +7 ( 8555) 37 – 78- 64
Tel/ fax : +7 ( 8555) 37 – 74 - 92
E-mail : inform@nknh.ru
Internet: www nknh.ru

 
Nizhnekamskneftekhim Inc. @ 2005