It
keeps to the schedule.
The Facility’s construction budget amounts to RUR 1566m.
To-date, it consumed over 70% of the planned investment.
Polymerization section equipment has been fully installed;
granulation and packaging section equipment is being installed
and piped; cooling tower and bead product silos are under
erection.
PS granulation and packaging line at second facility is
being equipped with a dust collecting system. Product packaging
and palletizing will be automatic.
According to A.
Minullin, PS PLANT director, erection of metal structures,
instrumentation and electrical equipment is planned for
completion in current March-April. Precommissioning is scheduled
for beginning in May.
With second facility in operation, PS capacity will total
100 000 TPA.
Press service
Nizhnekamskneftekhim Inc.